Discuss and Take Possible Action Regarding the Status, Prioritization, and Funding of Capital Projects |
BACKGROUND/DISCUSSION: USDA PROGRAM(S) & OTHER INITIATIVES
USDA Capital Program:
Phase 1
Water Line Replacement Projects:
-
- The WIFA/USDA funded water line replacement project Dashboard Report is online.
Construction Activities:
- White Oak/Cedar Meadows: Construction has been finished on the original project.
- The Permit for Approval to Construct is in process with ADEQ.
- The scope of the Change Order has been approved.
- Portals 1 & 2: Construction is scheduled to finish November 29, 2024. The project is on schedule.
- The contractor has started pressure testing the main pipeline.
- Continue working on installing service lines.
- Continue working on paving in the roadway areas where the waterline was installed.
Deep Well Project SV3
- Well Equipment, Booster Station, Water Storage Tank, and associated equipment bid opening is scheduled for October 24,2024.
USDA Capital Program
Interim Financing from WIFA for USDA Projects
- PSWID continues to process WIFA construction loan funds for disbursements requests on active construction projects.
- Sunrise Engineering continues to provide the USDA required, full time Resident Project Representative (RPR) construction observation services.
Non-USDA/WIFA Project Initiatives:
- Well and Water Production Infrastructure-
- District Staff continue work related to the inspection, well capacity testing, repair, and improvement of existing wells and booster stations to maintain water system reliability to meet summer water demands.
-
- EUSI is available to consult on well and system status with District Staff.
WIFA Project Meeting Items Review and Action:
- Review the USDA project list and procurement issues.
- WIFA Disbursements are reviewed and processed.
- Project Issues are addressed.
- EUSI personnel make construction project site visits to observe construction activities.
- EUSI personnel accompany District Staff as requested on field site visits and discuss water system and project issues.
- EUSI staff check the status of the WIFA Labor Boards on active projects.