View-PDF
 
 
PINE-STRAWBERRY WATER IMPROVEMENT DISTRICT

Board Action Item

 

MEETING DATE:

 

July 27, 2023

AGENDA ITEM: 6.b
PRESENTER: Paul Hendricks
SUBJECT: Discuss and Take Possible Action Regarding the Status, Prioritization, and Funding of Capital Projects

 

BACKGROUND/DISCUSSION: USDA PROGRAM(S) & OTHER INITIATIVES

 

USDA Capital Program:

Phase 1-

Waterline Replacement Projects:

    • We have been requested to post an overall status of all WIFA/USDA funded projects to the one-page public Dashboard Report for the Cool Pines Waterline Replacement Project.

Construction Activities:

    • Cool Pines Phase “A”: Contractor is 69% complete for pipeline replacement.
    • Woodland Heights: The Contractor has indicated that they may commence work sooner than the NTP date September 18, 2023 with construction scheduled to be completed in early February 2024.
    • Whispering Pines: 100 Calendar Days of construction, construction scheduled to start October 23, 2023.
    • White Oak/Cedar Meadows:  150-180 Calendar Days of construction, construction scheduled to start April 8, 2024.

Deep Well Project

  • The Deep Well will take approximately 150 Calendar Days for drilling and testing with a planned start (NTP) date September 11, 2023.
  • The electrical design engineer has contacted APS to determine the requirements to bring adequate power to the site. A meeting is scheduled for August 3rd with APS, Electrical Engineer and PSWID to review the electrical requirements for the new well.

Portals 1 & 2- Water Line Replacement

  • The review of the 95% plans from Sunrise has been completed. Once the final plans have been completed, bidding is scheduled for September 2023.
  • Geophysical testing has been performed to determine the best replacement alignment for the pipeline to minimize excessive hard dig and rock conditions.
  • The Engineers estimate for the project is $6,100,000 to install 17,100 LF of 6” PVC pipe.

USDA Capital Program

  • Interim Financing from WIFA for USDA Projects
    • The District continues to process WIFA construction loan funds for disbursements requests on active construction projects.
    • Sunrise Engineering continues to provide the USDA required, full time Resident Project Representative (RPR) construction observation services.

 

Non-USDA/WIFA Project Initiatives:

  • Well and Water Production Infrastructure
    • District Staff continues work related to the inspection, repair, and improvement of existing wells and booster stations to maintain water system reliability to meet summer water demands.
    • Tomahawk and Milk Ranch tanks will require recoating to prevent tank corrosion and maintain a sanitary surface.
  • Critical Water Leak Detection Activities-
    • The project team is reviewing the water system leak response program.

WIFA Project Meeting Items Review and Action:

  • Review the USDA project list and procurement issues.
  • WIFA Disbursements are reviewed and processed.
  • Project Issues are addressed.
  • EUSI personnel make construction project site visits to observe construction activities.
  • EUSI personnel accompany District Staff as needed on field site visits and discuss water system and project issues.
  • District Staff continue working on leak response and detection activities.
  • Well Status Assignment Logs and USDA Assignment Logs are updated and maintained.
  • EUSI staff check on the status of the WIFA Labor Boards on active projects.

 

The owner of this website has made a commitment to accessibility and inclusion, please report any problems that you encounter using the contact form on this website. This site uses the WP ADA Compliance Check plugin to enhance accessibility.