View-PDF
 
 
PINE-STRAWBERRY WATER IMPROVEMENT DISTRICT

Board Action Item

 

MEETING DATE:

 

July 27, 2023

AGENDA ITEM: 6.b
PRESENTER: Paul Hendricks
SUBJECT: Discuss and Take Possible Action Regarding the Status, Prioritization, and Funding of Capital Projects

 

BACKGROUND/DISCUSSION: USDA PROGRAM(S) & OTHER INITIATIVES

 

USDA Capital Program:

Phase 1-

Waterline Replacement Projects:

    • We have been requested to post an overall status of all WIFA/USDA funded projects to the one-page public Dashboard Report for the Cool Pines Waterline Replacement Project.

Construction Activities:

    • Cool Pines Phase “A”: Contractor is 69% complete for pipeline replacement.
    • Woodland Heights: The Contractor has indicated that they may commence work sooner than the NTP date September 18, 2023 with construction scheduled to be completed in early February 2024.
    • Whispering Pines: 100 Calendar Days of construction, construction scheduled to start October 23, 2023.
    • White Oak/Cedar Meadows:  150-180 Calendar Days of construction, construction scheduled to start April 8, 2024.

Deep Well Project

  • The Deep Well will take approximately 150 Calendar Days for drilling and testing with a planned start (NTP) date September 11, 2023.
  • The electrical design engineer has contacted APS to determine the requirements to bring adequate power to the site. A meeting is scheduled for August 3rd with APS, Electrical Engineer and PSWID to review the electrical requirements for the new well.

Portals 1 & 2- Water Line Replacement

  • The review of the 95% plans from Sunrise has been completed. Once the final plans have been completed, bidding is scheduled for September 2023.
  • Geophysical testing has been performed to determine the best replacement alignment for the pipeline to minimize excessive hard dig and rock conditions.
  • The Engineers estimate for the project is $6,100,000 to install 17,100 LF of 6” PVC pipe.

USDA Capital Program

  • Interim Financing from WIFA for USDA Projects
    • The District continues to process WIFA construction loan funds for disbursements requests on active construction projects.
    • Sunrise Engineering continues to provide the USDA required, full time Resident Project Representative (RPR) construction observation services.

 

Non-USDA/WIFA Project Initiatives:

  • Well and Water Production Infrastructure
    • District Staff continues work related to the inspection, repair, and improvement of existing wells and booster stations to maintain water system reliability to meet summer water demands.
    • Tomahawk and Milk Ranch tanks will require recoating to prevent tank corrosion and maintain a sanitary surface.
  • Critical Water Leak Detection Activities-
    • The project team is reviewing the water system leak response program.

WIFA Project Meeting Items Review and Action:

  • Review the USDA project list and procurement issues.
  • WIFA Disbursements are reviewed and processed.
  • Project Issues are addressed.
  • EUSI personnel make construction project site visits to observe construction activities.
  • EUSI personnel accompany District Staff as needed on field site visits and discuss water system and project issues.
  • District Staff continue working on leak response and detection activities.
  • Well Status Assignment Logs and USDA Assignment Logs are updated and maintained.
  • EUSI staff check on the status of the WIFA Labor Boards on active projects.