USDA CIP Report – 2024-02-20

   PSWID USDA CIP Program FY21 thru FY26     Fiscal Year to Date Thru June 2024                               Approved  Project Budget                     PSWID USDA CIP PROGRAM FY21 THRU FY26   Approved Budget Changes Approved Revised Budget Total Costs to Date FY...

WIFA Design Loan Funding Report – 2024-02-20

WIFA USDA ENGINEERING PROJECTS FUNDING FY21 thru FY26   Fiscal Year to Date Thru June 2024       PER APPROVED   Disbursements  Disbursements        Uses by Budget Item PHASE BUDGET   To Date To Date Total Funding to Remaining   Design & Engineering   $2,500,000.00...

PSWID Vice Chairman Report – 2024-03-28

PINE-STRAWBERRY WATER IMPROVEMENT DISTRICT Board Action Item MEETING DATE: Mar 28, 2024 AGENDA ITEM: 6E PRESENTER: George Gorkowski SUBJECT: Vice Chairman’s Report Moratorium Update We began releasing 5 new meters each month starting in September and have been...