PINE-STRAWBERRY WATER IMPROVEMENT DISTRICT

Board Action Item

 

MEETING DATE:

 

July 25, 2024

AGENDA ITEM:

6.b

PRESENTER:

Paul Hendricks

SUBJECT:

Discuss and Take Possible Action Regarding the Status, Prioritization, and Funding of Capital Projects

 


BACKGROUND/DISCUSSION: USDA PROGRAM(S) & OTHER INITIATIVES

USDA Capital Program:

Phase 1

Water Line Replacement Projects:

    • The WIFA/USDA funded water line replacement project Dashboard Report is online. 

Construction Activities

    • Woodland Heights:  Received Approval of Construction from ADEQ. Will proceed to close out the Contractors contract and USDA and WIFA paperwork. 
    • White Oak/Cedar Meadows:  Construction of 6” pipe is scheduled to finish October 5, 2024. The project is slightly ahead of schedule.
      • Total footage completed as of 7/19/24 is 4,555 LF 6” pipe.
      • The contractor will be pressure testing pipelines and installing services.
      • A Change Order is being processed to connect an additional area that will complete waterline replacements in the area.
      • The next phase of the work will include pavement and site restoration. 
    • Portals 1 & 2: Construction of 6” pipe is scheduled to finish November 29, 2024. The project is on schedule.
      • Total footage completed as of 7/19/24 is 5,000 LF 6” pipe, or approximately 40%.
      • The contractor has several crews working in the area to improve efficiency.
      • Trenching and main line installation is the primary focus.
      • Numerous utility location issues have occurred.
      • There have also been some areas of hard digging.
        The District is installing a new intermediate booster station.

Deep Well Project SV3

  • The well is planned to be completed to a total depth of 2,000 feet.
  • The installation of 1,650 feet of 10” casing was suspended due to the court order.
  • The ADEQ approved the Approval to Construct permit for the Well Equipment, Booster Station, Water Storage Tank, and associated equipment.
  • The advertisement and bidding are now scheduled with bid opening in late October.

USDA Capital Program

Interim Financing from WIFA for USDA Projects

  • PSWID continues to process WIFA construction loan funds for disbursements requests on active construction projects.
  • Sunrise Engineering continues to provide the USDA required, full time Resident Project Representative (RPR) construction observation services.

 

Non-USDA/WIFA Project Initiatives:

  • Well and Water Production Infrastructure-
    • District Staff continue work related to the inspection, well capacity testing, repair, and improvement of existing wells and booster stations to maintain water system reliability to meet summer water demands.
    • Well Status Logs are reviewed and updated. 

WIFA Project Meeting Items Review and Action:

  • Review the USDA project list and procurement issues.
  • WIFA Disbursements are reviewed and processed.
  • Project Issues are addressed.
  • EUSI personnel make construction project site visits to observe construction activities.
  • EUSI personnel accompany District Staff as needed on field site visits and discuss water system and project issues.
  • EUSI staff check the status of the WIFA Labor Boards on active projects.