PINE-STRAWBERRY WATER IMPROVEMENT DISTRICT
Board Action Item
MEETING DATE: |
July 25, 2024 |
AGENDA ITEM: |
6.b |
PRESENTER: |
Paul Hendricks |
SUBJECT: |
Discuss and Take Possible Action Regarding the Status, Prioritization, and Funding of Capital Projects |
BACKGROUND/DISCUSSION: USDA PROGRAM(S) & OTHER INITIATIVES
USDA Capital Program:
Phase 1
Water Line Replacement Projects:
-
- The WIFA/USDA funded water line replacement project Dashboard Report is online.
Construction Activities:
-
- Woodland Heights: Received Approval of Construction from ADEQ. Will proceed to close out the Contractors contract and USDA and WIFA paperwork.
-
- White Oak/Cedar Meadows: Construction of 6” pipe is scheduled to finish October 5, 2024. The project is slightly ahead of schedule.
-
-
- Total footage completed as of 7/19/24 is 4,555 LF 6” pipe.
- The contractor will be pressure testing pipelines and installing services.
- A Change Order is being processed to connect an additional area that will complete waterline replacements in the area.
- The next phase of the work will include pavement and site restoration.
-
-
- Portals 1 & 2: Construction of 6” pipe is scheduled to finish November 29, 2024. The project is on schedule.
- Total footage completed as of 7/19/24 is 5,000 LF 6” pipe, or approximately 40%.
- The contractor has several crews working in the area to improve efficiency.
- Trenching and main line installation is the primary focus.
- Numerous utility location issues have occurred.
- There have also been some areas of hard digging.
The District is installing a new intermediate booster station.
- Portals 1 & 2: Construction of 6” pipe is scheduled to finish November 29, 2024. The project is on schedule.
Deep Well Project SV3
- The well is planned to be completed to a total depth of 2,000 feet.
- The installation of 1,650 feet of 10” casing was suspended due to the court order.
- The ADEQ approved the Approval to Construct permit for the Well Equipment, Booster Station, Water Storage Tank, and associated equipment.
- The advertisement and bidding are now scheduled with bid opening in late October.
USDA Capital Program
Interim Financing from WIFA for USDA Projects
- PSWID continues to process WIFA construction loan funds for disbursements requests on active construction projects.
- Sunrise Engineering continues to provide the USDA required, full time Resident Project Representative (RPR) construction observation services.
Non-USDA/WIFA Project Initiatives:
- Well and Water Production Infrastructure-
-
- District Staff continue work related to the inspection, well capacity testing, repair, and improvement of existing wells and booster stations to maintain water system reliability to meet summer water demands.
-
- Well Status Logs are reviewed and updated.
WIFA Project Meeting Items Review and Action:
- Review the USDA project list and procurement issues.
- WIFA Disbursements are reviewed and processed.
- Project Issues are addressed.
- EUSI personnel make construction project site visits to observe construction activities.
- EUSI personnel accompany District Staff as needed on field site visits and discuss water system and project issues.
- EUSI staff check the status of the WIFA Labor Boards on active projects.