View-PDF

PINE-STRAWBERRY WATER IMPROVEMENT DISTRICT

Board Action Item

 

MEETING DATE:

 

September 26, 2024

AGENDA ITEM:

6.b

PRESENTER:

Paul Hendricks

SUBJECT:

Discuss and Take Possible Action Regarding the Status, Prioritization, and Funding of Capital Projects


BACKGROUND/DISCUSSION: USDA PROGRAM(S) & OTHER INITIATIVES

USDA Capital Program:

Phase 1

Water Line Replacement Projects:

    • The WIFA/USDA funded water line replacement project Dashboard Report is online.

Construction Activities

  • White Oak/Cedar Meadows:  Construction is scheduled to finish October 5, 2024. Cedar Meadow – 100% of the 5,358 LF of water line has been installed.
    • The contractor has completed pressure testing the pipelines and all services have been installed.
    • The cost for the Change Order is being reviewed prior to processing for funding approval.
    • The Permit for Approval to Construct is in process with ADEQ.
  • Portals 1 & 2: Construction is scheduled to finish November 29, 2024. The project is on schedule. 100% of the 12,278 LF of water line has been installed.
    • The contractor has started pressure testing the main pipeline.
    • There are 8 more services to be completed.
    • Paving has started in the roadway areas where the waterline was installed.

Deep Well Project SV3

  • The pre bid meeting was held September 5, 2024 for the Well Equipment, Booster Station, Water Storage Tank, and associated equipment.
  • The bid opening is scheduled for October 24,2024.

USDA Capital Program

Interim Financing from WIFA for USDA Projects

  • PSWID continues to process WIFA construction loan funds for disbursements requests on active construction projects.
  • Sunrise Engineering continues to provide the USDA required, full time Resident Project Representative (RPR) construction observation services. 

Non-USDA/WIFA Project Initiatives:

  • Well and Water Production Infrastructure-
    • District Staff continue work related to the inspection, well capacity testing, repair, and improvement of existing wells and booster stations to maintain water system reliability to meet summer water demands.
    • EUSI reviews well status with District Staff. 

WIFA Project Meeting Items Review and Action:

  • Review the USDA project list and procurement issues.
  • WIFA Disbursements are reviewed and processed.
  • Project Issues are addressed.
  • EUSI personnel make construction project site visits to observe construction activities.
  • EUSI personnel accompany District Staff as requested on field site visits and discuss water system and project issues.
  • EUSI staff check the status of the WIFA Labor Boards on active projects.
The owner of this website has made a commitment to accessibility and inclusion, please report any problems that you encounter using the contact form on this website. This site uses the WP ADA Compliance Check plugin to enhance accessibility.