  1. Water loss for April is about 60,000 with 4 leaks.
  2. Pinecove project is done and working very well.
  3. We have a new project out for bid and hope to get that done soon.
  4. As of 5-5-2025 the field crew will be changing there hours to 5am to 1:30pm.
  5. We have ordered a few trees and bushes to plant at the SV3 site. We plan to plant these on 5-1.