 PSWID USDA CIP Program FY21 thru FY26
 | 
  | 
|   | 
  | 
  | 
|   | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
|   | 
  | 
Approved  Project Budget | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
|   | 
PSWID USDA CIP PROGRAM FY21 THRU FY26 | 
  | 
Approved Budget Changes | 
Approved Revised Budget | 
Total Costs to Date FY 2023 | 
Total Costs to Date FY 2024 | 
Total Costs to Date FYE 2025 | 
Total Costs to Date FY 2025 | 
Total Costs to Date | 
FY 25 CIP Remaining Budget | 
Project % Complete to Date | 
| Project # | 
PROJECT NAME | 
PHASE | 
  | 
  | 
All Costs | 
All Costs | 
Eng & Non-Eng | 
Construction | 
ALL | 
  | 
  | 
| 1 | 
Strawberry Creek Foothills/Strawberry Pines Waterline | 
$3,630,883.00 | 
1 | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
$3,630,883.00 | 
  | 
| 2 | 
RW/MME2/SMS/Fitz-Strawberry Waterline Replacement | 
$5,080,358.00 | 
1 | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
$5,080,358.00 | 
  | 
| 3 | 
Strawberry View 3/Shady Lane Waterline Replacement | 
$3,535,788.00 | 
1 | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
$3,535,788.00 | 
  | 
| 4 | 
Strawberry View 1&2 Waterline Replacement | 
$3,722,603.00 | 
1 | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
$3,722,603.00 | 
  | 
| 5 | 
Portals 1, 2 & 3 Waterline Replacement-C/O #1 Engineering Credit | 
$5,518,758.00 | 
1 | 
-$141,150.00 | 
$5,377,608.00 | 
$242,751.50 | 
$1,823,368.77 | 
  | 
$1,190,650.61 | 
$3,256,770.88 | 
$2,120,837.12 | 
60.56% | 
| 6 | 
Whispering Pines Waterline Replacement-C/O #1 Engineering Credit | 
$421,083.00 | 
1 | 
$162,006.46 | 
$583,089.46 | 
$69,807.80 | 
$513,281.66 | 
  | 
  | 
$583,089.46 | 
$0.00 | 
100.00% | 
| 7 | 
Cool Pines Phase A Waterline Replacement-C/O #1 Engineering Credit | 
$805,064.00 | 
1 | 
$759,328.63 | 
$1,564,392.63 | 
$949,906.69 | 
$614,485.94 | 
  | 
  | 
$1,564,392.63 | 
$0.00 | 
100.00% | 
| 8 | 
Woodland Heights Phase A Waterline Replacement | 
$0.00 | 
1 | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
| 9 | 
Woodland Heights Phase B &C Waterline Replacement-Combined-Amend #1 | 
$2,948,415.00 | 
1 | 
-$26,646.98 | 
$2,921,768.02 | 
$803,502.30 | 
$2,118,265.72 | 
  | 
  | 
$2,921,768.02 | 
$0.00 | 
100.00% | 
| 10 | 
Pine Mountain Acres/Pinion Waterline Replacement-Deleted | 
$0.00 | 
1 | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
$0.00 | 
  | 
| 11 | 
White Oak/Cedar Meadows Waterline Replacement-MHE C/O #2-C/O #2 Engineering | 
$684,612.00 | 
1 | 
$950,083.84 | 
$1,634,695.84 | 
$152,829.23 | 
$704,349.11 | 
$73,229.32 | 
$353,546.54 | 
$1,283,954.20 | 
$350,741.64 | 
187.54% | 
| 12 | 
Hidden Pines Waterline Replacement | 
$450,156.00 | 
1 | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
$450,156.00 | 
  | 
| 13 | 
Cimmaron Pines Waterline Replacement | 
$1,219,173.00 | 
1 | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
$1,219,173.00 | 
  | 
| 14 | 
Brookview Terrace 1 & 2 Waterline Replacement | 
$1,410,360.00 | 
1 | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
$1,410,360.00 | 
  | 
| 15 | 
Strawberry Mtn Shadows 1&2/Pine Cove Waterline Replacement | 
$4,689,125.00 | 
1 | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
$4,689,125.00 | 
  | 
| 16 | 
Strawberry Mtn Shadows 2 Service Corp Stop Replacement | 
$466,233.00 | 
1 | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
$466,233.00 | 
  | 
|   | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
|   | 
USDA WATERLINE PROJECTS | 
$34,582,611.00 | 
  | 
$1,703,621.95 | 
$12,081,553.95 | 
$2,218,797.52 | 
$5,773,751.20 | 
$73,229.32 | 
$1,544,197.15 | 
$9,609,975.19 | 
$26,676,257.76 | 
  | 
|   | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
| 17 | 
MRTank-SV3 Tank/Booster Bldg/Well  Pump, Etc. | 
$305,915.00 | 
1 | 
  | 
$305,915.00 | 
  | 
  | 
  | 
  | 
  | 
$305,915.00 | 
  | 
| 18 | 
System Wide Scada | 
$549,000.00 | 
1 | 
  | 
$549,000.00 | 
  | 
  | 
  | 
  | 
  | 
$549,000.00 | 
  | 
| 19 | 
System Wide Water Model | 
$300,000.00 | 
1 | 
  | 
$300,000.00 | 
$262,709.22 | 
$23,798.75 | 
$6,326.25 | 
$0.00 | 
$292,834.22 | 
$7,165.78 | 
97.61% | 
|   | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
|   | 
USDA OTHER PROJECTS | 
$1,154,915.00 | 
  | 
$0.00 | 
$1,154,915.00 | 
$262,709.22 | 
$23,798.75 | 
$6,326.25 | 
$0.00 | 
$292,834.22 | 
$862,080.78 | 
  | 
|   | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
| 1 | 
Strawberry Ranch PZ Deep Well-KP C/O $327,470.60-GL C/O $47,876 | 
$2,059,571.00 | 
2 | 
$466,966.60 | 
$2,526,537.60 | 
$50,296.91 | 
$1,426,163.87 | 
$4,459.60 | 
  | 
$1,480,920.38 | 
$1,045,617.22 | 
71.90% | 
|   | 
  | 
$2,059,571.00 | 
  | 
$466,966.60 | 
$2,526,537.60 | 
$50,296.91 | 
$1,426,163.87 | 
$4,459.60 | 
$0.00 | 
$1,480,920.38 | 
$1,045,617.22 | 
  | 
|   | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
|   | 
TOTAL PROJECTS | 
$37,797,097.00 | 
  | 
$2,170,588.55 | 
$15,763,006.55 | 
$2,531,803.65 | 
$7,223,713.82 | 
$84,015.17 | 
$1,544,197.15 | 
$11,383,729.79 | 
$26,413,367.21 | 
  | 
|   | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
|   | 
PNC Bank Payoff | 
$4,000,000.00 | 
  | 
  | 
$4,000,000.00 | 
$3,646,269.09 | 
$0.00 | 
  | 
$0.00 | 
$3,646,269.09 | 
$353,730.91 | 
91.16% | 
|   | 
Interim Financing Fees | 
$1,200,000.00 | 
  | 
  | 
$1,200,000.00 | 
$0.00 | 
$0.00 | 
  | 
$0.00 | 
$0.00 | 
$1,200,000.00 | 
0.00% | 
|   | 
Legal Fees | 
$116,733.00 | 
  | 
  | 
$116,733.00 | 
$24,805.56 | 
$2,252.50 | 
$265.00 | 
$0.00 | 
$27,323.06 | 
$89,409.94 | 
23.41% | 
|   | 
Single Audit Fees | 
$15,000.00 | 
  | 
  | 
$15,000.00 | 
$3,750.00 | 
$4,100.00 | 
$3,000.00 | 
$0.00 | 
$10,850.00 | 
$4,150.00 | 
72.33% | 
|   | 
Program Management Fees | 
$1,316,768.00 | 
  | 
  | 
$1,316,768.00 | 
$145,726.63 | 
$282,042.08 | 
$68,107.22 | 
$0.00 | 
$495,875.93 | 
$820,892.07 | 
37.66% | 
|   | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
|   | 
USDA OTHER FEES | 
$6,648,501.00 | 
  | 
$0.00 | 
$6,648,501.00 | 
$3,820,551.28 | 
$288,394.58 | 
$71,372.22 | 
$0.00 | 
$4,180,318.08 | 
$2,468,182.92 | 
  | 
|   | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
|   | 
TOTAL PER USDA PROJECT SCHEDULE-ADJUSTED | 
$44,445,598.00 | 
  | 
$2,170,588.55 | 
$22,411,507.55 | 
$6,352,354.93 | 
$7,512,108.40 | 
$155,387.39 | 
$1,544,197.15 | 
$15,564,047.87 | 
$28,881,550.13 | 
  | 
|   | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
  | 
$11,917,778.78 | 
$28,881,550.13 | 
  |