PSWID – USDA CONTRACTS |
|||||
Project Schedule |
|||||
Project Name |
Contractor |
Contract Date |
NTP Sign |
Contract |
Contract |
|
|
|
Date |
Start |
Completion |
|
|
|
|
Time |
Date |
Woodland Heights |
Mountain High Excavating |
3/23/2023 |
4/12/2023 |
9/18/2023 |
3/16/2024 |
Cool Pines Phase A |
Mountain High Excavating |
3/23/2023 |
4/18/2023 |
4/24/2023 |
10/11/2023 |
Whispering Pines |
Apache Underground |
3/23/2023 |
4/20/2023 |
10/23/2023 |
3/1/2024 |
White Oak/Cedar Meadow |
Mountain High Excavating |
4/27/2023 |
5/23/2023 |
4/8/2024 |
10/5/2024 |
Portals 1 & 2 |
Designed – Bid in |
|
|
|
|
Strawberry Deep Well |
KP Ventures Well Drilling |
3/23/2023 |
4/13/023 |
9/11/2023 |
2/11/2024 |
Pine-Strawberry Water Improvement District
6306 W. Hardscrabble Mesa Rd, Pine, AZ 85544
PHONE (928) 476-4222
FAX (928) 472-4224
MAILING: PO Box 134, Pine, AZ 85544