WIFA USDA ENGINEERING PROJECTS FUNDING FY21 thru FY26-FINAL  
Fiscal Year to Date Thru June 2025  
    PER APPROVED   Disbursements  Disbursements       
Uses by Budget Item PHASE BUDGET   To Date To Date Total Funding to Remaining  
Design & Engineering   $2,500,000.00   6/30/2024 6/30/2025 Date 6/30/2025 Balance  
Total Funding Budget   $2,500,000.00   $1,361,365.27 $49,325.10 $1,410,690.37 $1,089,309.63  
            Deobligated 9/11/2024 $1,089,309.63  
            Remaining Balance $0.00  
    PER APPROVED Engineering Funding to Funding to Total Funding to Remaining  
WIFA PSWID USDA PROJECTS FUNDING FY21 THRU FY2024   BUDGET  Contract FYE 6/30/2024 FYE 6/30/2025 Date 6/30/2025 Balance % Complete to Date
PROJECT NAME   PROJECTS Revised          
Strawberry Creek Foothills/Strawberry Pines Waterline   $280,497.00            
RW/MME2/SMS/Fitz-Strawberry Waterline Replacement   $400,199.00            
Strawberry View 3/Shady Lane Waterline Replacement   $273,151.00            
Strawberry View 1&2 Waterline Replacement 2 $287,583.00            
Portals 1, 2 & 3 Waterline Replacement+Permit Fee 2 $459,897.00 $273,376.50 $273,376.50 $0.00 $273,376.50 $0.00 100.00%
Whispering Pines Waterline Replacement + Permit Fee 1 $32,530.00 $67,817.49 $67,817.49 $0.00 $67,817.49 $0.00 100.00%
Cool Pines Phase A Waterline Replacement + Permit Fee+Amend #1 1 $67,089.00 $109,185.07 $109,185.07 $0.00 $109,185.07 $0.00 100.00%
Woodland Heights Phase A, B & C Waterline Replacement+Amend #1 1 $241,437.00 $284,571.47 $284,571.47 $0.00 $284,571.47 $0.00 100.00%
Woodland Heights Phase -Combined 1 $0.00            
Pine Mountain Acres/Pinion Waterline Replacement-Removed 1 $0.00            
White Oak/Cedar Meadows Waterline Replacement+Amendment #1+Permit Fee 1 $52,889.00 $178,417.20 $150,461.20 $27,956.00 $178,417.20 $0.00 100.00%
Hidden Pines Waterline Replacement   $34,776.00       $0.00 $0.00  
Cimmaron Pines Waterline Replacement   $94,185.00       $0.00 $0.00  
Brookview Terrace 1 & 2 Waterline Replacement   $117,530.00       $0.00 $0.00  
Strawberry Mtn Shadows 1&2/Pine Cove Waterline Replacement   $362,250.00       $0.00 $0.00  
Strawberry Mtn Shadows 2 Service Corp Stop Replacement   $36,018.00       $0.00 $0.00  
Milk Ranch Tank – Changed to Strawberry View 3 Tank 2 $30,090.00       $0.00 $0.00  
System Wide Scada 2 $100,000.00       $0.00 $0.00  
System Wide Water Model 2 $300,000.00 $292,774.22 $282,256.97 $10,517.25 $292,774.22 $0.00 100.00%
Strawberry Ranch PZ Deep Well  2 $199,956.00 $200,692.84 $190,270.89 $10,421.95 $200,692.84 $0.00 100.00%
Publication Ads – All Projects 2 $4,000.00 $3,855.58 $3,425.68 $429.90 $3,855.58 $0.00 100.00%
                 
TOTAL USDA ENGINEERING COSTS   $3,374,077.00 $1,406,834.79 $1,361,365.27 $49,325.10 $1,410,690.37 $0.00