WIFA WATER CONSERVATION GRANT PROJECTS, FUNDING AND COSTS FY23 thru FY26

Fiscal Year to Date Thru June 2025

  PER APPROVED Disbursements  Funding Received  
Uses by Budget Item GRANT To Date To Date Total Funding Due
    6/30/2025 6/30/2025 Date 6/30/2025
Construction & Non-Construction-Grant Portion $1,575,675.00 $333,266.20 $22,587.59 $310,678.61
Construction & Non-Construction-District Portion $525,225.00 $131,489.66 $0.00 $0.00
Total Funding Budget $2,100,900.00 $464,755.86 $22,587.59 $310,678.61
         
         
  PER APPROVED COSTS COSTS Remaining Budget
WIFA PSWID GRANT PROJECTS COSTS FY23 THRU FY2026 BUDGET   1/31/2025 FYE 6/30/2025 Date 6/30/2025
PROJECT NAME PROJECTS      
Pine Cove Project – Engineering $43,064.91 $43,064.91 $43,064.91 $0.00
Pine Cove Project – MHI Construction-Includes 2 Change Orders $1,507,460.27 $412,161.30 $412,161.30 $1,095,298.97
Cemetery Road Project – Engineering $22,349.28 $9,336.87 $9,336.87 $13,012.41
Cemetery Road Project – Plans not complete or awarded $0.00 $0.00 $0.00 $0.00
Payson Roundup Publication Fees – Not reimbursable $192.78 $192.78 $192.78 $0.00
         
Total Budget and Costs to Date $1,573,067.24 $464,755.86 $464,755.86 $1,108,311.38
         
Total Remaining Grant & District Funding Available $527,832.76