View-PDF

PINE-STRAWBERRY WATER IMPROVEMENT DISTRICT

Board Action Item

 

MEETING DATE:

 

June 27, 2024

AGENDA ITEM:

6.b

PRESENTER:

Paul Hendricks

SUBJECT:

Discuss and Take Possible Action Regarding the Status, Prioritization, and Funding of Capital Projects

 


BACKGROUND/DISCUSSION: USDA PROGRAM(S) & OTHER INITIATIVES

USDA Capital Program:

Phase 1

Water Line Replacement Projects:

    • The WIFA/USDA funded water line replacement project Dashboard Report is online.

Construction Activities

    • Woodland Heights: Final project documentation and project close out is in progress. 
    • White Oak/Cedar Meadows:  Construction of 4,500’ of 6” pipe is scheduled to finish October 5, 2024.
      • Total footage completed as of 6/21/24
      • 3550 LF 6” pipe
    • Portals 1 & 2: Construction of 12,278’ of 6” pipe is scheduled to finish November 29, 2024.
      • Total footage completed as of 6/21/24
      • 3550 LF 6” pipe

Deep Well Project SV3

  • The well is planned to be completed to a total depth of 2,000 feet.
  • The installation of 1,650 feet of 10” casing was suspended due to the court order.
  • The design engineer has prepared the design documents for submittal to ADEQ.
  • APS is working with PSWID, and potential landowners related to routing options for the delivery of 3-phase power to the new well site.

 USDA Capital Program

Interim Financing from WIFA for USDA Projects

  • PSWID continues to process WIFA construction loan funds for disbursements requests on active construction projects.
  • Sunrise Engineering continues to provide the USDA required, full time Resident Project Representative (RPR) construction observation services. 

Non-USDA/WIFA Project Initiatives:

  • Well and Water Production Infrastructure
    • District Staff continue work related to the inspection, well capacity testing, repair, and improvement of existing wells and booster stations to maintain water system reliability to meet summer water demands.
    • Well Status Logs are reviewed and updated. 

WIFA Project Meeting Items Review and Action:

  • Review the USDA project list and procurement issues.
  • WIFA Disbursements are reviewed and processed.
  • Project Issues are addressed.
  • EUSI personnel make construction project site visits to observe construction activities.
  • EUSI personnel accompany District Staff as needed on field site visits and discuss water system and project issues.
  • EUSI staff check the status of the WIFA Labor Boards on active projects.
The owner of this website has made a commitment to accessibility and inclusion, please report any problems that you encounter using the contact form on this website. This site uses the WP ADA Compliance Check plugin to enhance accessibility.