View-PDF

PINE-STRAWBERRY WATER IMPROVEMENT DISTRICT

Board Action Item

 

MEETING DATE:

 

 December 5, 2024

AGENDA ITEM:

6.A

PRESENTER:

Paul Hendricks

SUBJECT:

Discuss and Take Possible Action Regarding the Status, Prioritization, and Funding of Capital Projects


BACKGROUND/DISCUSSION: USDA PROGRAM(S) & OTHER INITIATIVES

USDA Capital Program:

Phase 1

Water Line Replacement Projects:

  • The WIFA/USDA funded water line replacement project Dashboard Report is online. 

Construction Activities

  • White Oak/Cedar Meadows: Construction has been finished on the original project.
  • Work is nearly completed on the Change Order portion of the project.
  • Pinon – Installed 1700 feet of main water line. Working on extending service lines, 5 more to be completed.
  • Mistletoe – Potholing completed with remaining work on schedule.
  • Portals 1 & 2: Construction is scheduled to finish December 6, 2024. The remaining elements of the project are on schedule.
  • The contractor has completed pressure testing the main pipeline.
  • Completed installing service lines.
  • Completed paving in the roadway areas where the waterline was installed.
  • The contractor is working on punch list items.

Deep Well Project SV3

  • Well Equipment, Booster Station, Water Storage Tank, and associated equipment bid opening is scheduled for October 24,2024. PSWID has selected Summit Construction for the project. Value Engineering discussions are ongoing.
  • Received the ATC permit from ADEQ for project.

USDA Capital Program

Interim Financing from WIFA for USDA Projects

  • PSWID continues to process WIFA construction loan funds for disbursements requests on active construction projects.
  • Sunrise Engineering continues to provide the USDA required, full time Resident Project Representative (RPR) construction observation services on waterline projects. 

Non-USDA/WIFA Project Initiatives:

  • Well and Water Production Infrastructure-
  • District Staff continue work related to the inspection, capacity testing, repair, and improvement of existing wells and booster stations to maintain water system reliability to meet summer water demands.
    • EUSI is available to consult on well and system status with District Staff. 

WIFA Project Meeting Items Review and Action:

  • Review the USDA project list and procurement issues.
  • WIFA Disbursements are reviewed and processed.
  • Project Issues are addressed.
  • EUSI personnel make construction project site visits to observe construction activities.
  • EUSI personnel accompany District Staff as requested on field site visits and discuss water system and project issues.
  • EUSI staff check the status of the WIFA Labor Boards on active projects.