Board Action Item |
MEETING DATE: | April 25, 2024 |
AGENDA ITEM: | 6E |
PRESENTER: | George Gorkowski |
SUBJECT: | Vice Chairman’s Report |
Moratorium Update
We began releasing 5 new meters each month starting in September 2023 and have been monitoring the demand caused by the increase. There is no significant increase in demand. Actual water demand in March is down slightly from a year ago. This probably occurred from public water conservation efforts. Thank you from all at PSWID!
Current actions:
• Monitor the demand from water meter release plan.
• Continue to push forward on the development of the new “deep well”.
• Continue all pipe replacement projects and well rehabs.
Regards,
George Gorkowski
PSWID Vice Chairman