WIFA USDA CONSTRUCTION PROJECTS FUNDING FY22 thru FY27 |
Fiscal Year to Date Thru June 2025 |
|
PER APPROVED |
Disbursements |
Disbursements |
Disbursements |
|
|
Uses by Budget Item |
BUDGET |
To Date |
To Date |
To Date |
Total Funding to |
Remaining |
Construction & Non-Construction |
$17,500,000.00 |
6/30/2023 |
6/30/2024 |
6/30/2025 |
Date 6/30/2024 |
Balance |
Total Funding Budget |
$17,500,000.00 |
$888,157.27 |
$6,842,103.50 |
$1,760,160.53 |
$9,490,421.30 |
$8,009,578.70 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PER APPROVED |
Funding to |
Funding to |
Funding to |
Total Funding to |
Remaining |
WIFA PSWID USDA PROJECTS FUNDING FY22 THRU FY2027 |
BUDGET |
FYE 6/30/2023 |
FYE 6/30/2024 |
FYE 6/30/2025 |
Date 6/30/2025 |
Balance |
PROJECT NAME |
PROJECTS |
|
|
|
|
|
Portals 1&2 Waterline Replacement |
$5,039,058.00 |
|
$1,132,469.20 |
$1,206,913.75 |
$2,339,382.95 |
$2,699,675.05 |
Whispering Pines Waterline Replacement+Permit Fee+C/O’s 2&5 |
$514,761.31 |
$1,480.25 |
$513,281.06 |
$0.00 |
$514,761.31 |
$0.00 |
Cool Pines Phase A Waterline Replacement+Permit Fee+C/O’s 1-4 |
$1,454,697.20 |
$486,229.57 |
$968,467.63 |
$0.00 |
$1,454,697.20 |
$0.00 |
Woodland Heights Phase A, B & C Waterline Replacement+Amend #1 |
$2,636,633.51 |
$358,762.15 |
$2,277,871.36 |
$0.00 |
$2,636,633.51 |
$0.00 |
White Oak/Cedar Meadows Waterline Replacement+Amendment #1+Permit Fee |
$1,217,483.00 |
$1,422.50 |
$495,574.02 |
$394,166.09 |
$891,162.61 |
$326,320.39 |
Strawberry Replacement Deep Well – Phase 1 |
$2,159,382.01 |
|
$1,156,831.90 |
$60,435.95 |
$1,217,267.85 |
$942,114.16 |
Strawberry Replacement Deep Well – Phase 2 |
$2,008,136.97 |
|
|
$0.00 |
$0.00 |
$2,008,136.97 |
|
|
|
|
|
|
|
TOTAL CONTRUCTION COSTS |
$15,030,152.00 |
$847,894.47 |
$6,544,495.17 |
$1,661,515.79 |
$9,053,905.43 |
$5,976,246.57 |
Other Costs |
|
|
|
|
|
|
Legal Fees |
$116,733.00 |
$7,834.66 |
$2,491.00 |
$79.50 |
$10,405.16 |
$106,327.84 |
Inspection & Construction Management |
$1,101,615.00 |
$32,428.14 |
$270,624.61 |
$66,005.42 |
$369,058.17 |
$732,556.83 |
Administration |
$15,000.00 |
|
$4,100.00 |
$0.00 |
$4,100.00 |
$10,900.00 |
Interim Financing Interest Reimbursement |
$1,236,500.00 |
$0.00 |
$20,392.72 |
$32,559.82 |
$52,952.54 |
$1,183,547.46 |
Total Other Costs |
$2,469,848.00 |
$40,262.80 |
$297,608.33 |
$98,644.74 |
$436,515.87 |
$2,033,332.13 |
|
|
|
|
|
|
|
Total Funding |
$17,500,000.00 |
$888,157.27 |
$6,842,103.50 |
$1,760,160.53 |
$9,490,421.30 |
$8,009,578.70 |