WIFA USDA CONSTRUCTION PROJECTS FUNDING FY22 thru FY27 |
|
Fiscal Year to Date Thru June 2025 |
|
|
PER APPROVED |
Disbursements |
Disbursements |
Disbursements |
|
|
|
Uses by Budget Item |
BUDGET |
To Date |
To Date |
To Date |
Total Funding to |
Remaining |
|
Construction & Non-Construction |
$17,500,000.00 |
6/30/2023 |
6/30/2024 |
6/30/2025 |
Date 6/30/2025 |
Balance |
|
Total Funding Budget |
$17,500,000.00 |
$888,157.27 |
$6,842,103.50 |
$3,275,830.81 |
$11,006,091.58 |
$6,493,908.42 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
PER APPROVED |
Funding to |
Funding to |
Funding to |
Total Funding to |
Remaining |
PROJECT |
WIFA PSWID USDA PROJECTS FUNDING FY22 THRU FY2027 |
BUDGET |
FYE 6/30/2023 |
FYE 6/30/2024 |
FYE 6/30/2025 |
Date 6/30/2025 |
Balance |
NUMBER |
PROJECT NAME |
PROJECTS |
|
|
|
|
|
5 |
Portals 1&2 Waterline Replacement |
$5,039,058.00 |
|
$1,132,469.20 |
$2,406,521.61 |
$3,538,990.81 |
$1,500,067.19 |
6 |
Whispering Pines Waterline Replacement+Permit Fee+C/O’s 2&5 |
$514,761.31 |
$1,480.25 |
$513,281.06 |
$0.00 |
$514,761.31 |
$0.00 |
7 |
Cool Pines Phase A Waterline Replacement+Permit Fee+C/O’s 1-4 |
$1,454,697.20 |
$486,229.57 |
$968,467.63 |
$0.00 |
$1,454,697.20 |
$0.00 |
8 |
Woodland Heights Phase A, B & C Waterline Replacement+Amend #1 |
$2,636,633.51 |
$358,762.15 |
$2,277,871.36 |
$0.00 |
$2,636,633.51 |
$0.00 |
11 |
White Oak/Cedar Meadows Waterline Replacement+Amendment #1+PF&2 CHG ORDERS |
$1,647,355.45 |
$1,422.50 |
$495,574.02 |
$635,628.66 |
$1,132,625.18 |
$514,730.27 |
|
Strawberry Replacement Deep Well – Phase 1 |
$2,159,382.01 |
|
$1,156,831.90 |
$68,497.91 |
$1,225,329.81 |
$934,052.20 |
|
Strawberry Replacement Deep Well – Phase 2 |
$2,008,136.97 |
|
|
$0.00 |
$0.00 |
$2,008,136.97 |
|
|
|
|
|
|
|
|
|
TOTAL CONTRUCTION COSTS |
$15,460,024.45 |
$847,894.47 |
$6,544,495.17 |
$3,110,648.18 |
$10,503,037.82 |
$4,956,986.63 |
|
Other Costs |
|
|
|
|
|
|
|
Legal Fees |
$116,733.00 |
$7,834.66 |
$2,491.00 |
$344.50 |
$10,670.16 |
$106,062.84 |
|
Inspection & Construction Management |
$1,101,615.00 |
$32,428.14 |
$270,624.61 |
$129,278.31 |
$432,331.06 |
$669,283.94 |
|
Administration |
$15,000.00 |
|
$4,100.00 |
$3,000.00 |
$7,100.00 |
$7,900.00 |
|
Interim Financing Interest Reimbursement-Revised due to WO/CM Change Order |
$806,627.55 |
$0.00 |
$20,392.72 |
$32,559.82 |
$52,952.54 |
$753,675.01 |
|
Total Other Costs |
$2,039,975.55 |
$40,262.80 |
$297,608.33 |
$165,182.63 |
$503,053.76 |
$1,536,921.79 |
|
|
|
|
|
|
|
|
|
Total Funding |
$17,500,000.00 |
$888,157.27 |
$6,842,103.50 |
$3,275,830.81 |
$11,006,091.58 |
$6,493,908.42 |